<%@ page import="org.jasig.portal.security.provider.*" %> <%@ page import="org.jasig.portal.security.*" %> <%@ page import="java.util.*" %> <%@ page import="com.pipeline.bom.Person_3" %> <%@ page import="com.pipeline.bom.PersonManager_3" %> <%@ page import="com.pipeline.bom.BomManagerFactory" %> <%@ page import="com.pipeline.web.WebUtil" %> <%@ page import="java.net.*" %> <% //Check to see if this is the Google search appliance String googleApplianceAgent="gsa-crawler"; String userAgent = request.getHeader("User-Agent"); //index will be greater than 0 if the GSA is detected int index=userAgent.indexOf(googleApplianceAgent); //pass-through authentication ------------------------------------------------------ if (index < 0){ //if this is not the Google search appliance String username = ""; try{ SimplePersonManager doriPerson = new SimplePersonManager(); IPerson i = doriPerson.getPerson(request); String uid = (String)i.getAttribute("urn:sungardhe:dir:loginId"); //out.println(uid); username = uid; }catch (java.lang.NullPointerException e){ //user not logged in - redirect to login String theRedirectURL = "/cp/home/displaylogin?goto=" + URLEncoder.encode(request.getRequestURL().toString().replace("http://", "https://")); %> <% }catch (Exception e){ out.println("Error: " + e); } } //END pass-through authentication ------------------------------------------------------ %>
<% //put content in school frame if this is not the Google search appliance if (index < 0){ %> <% } %>

Facilities Management

2012 Design Construction Update

Summer 2012 Projects

Start Estimated Finish Date

Residence Life Buildings

Brottier Hall 
  Laundry Exhaust 4/9/12 6/1/12
  Boiler Room Ventilation 4/9/12 6/1/12
  Increase # of Handicap Units On Hold
  Renewal & Replacement Furniture 5/4/12 7/2/12
  Replace 6" Domestic Waterline
  Replace Front Entry Pavers 5/7/12 5/28/12
Des Places
  Des Place New Construction 5/7/12 8/6/12
  Promenade Sidewalk 3/14/12 6/6/12
  Seitz Street Repaving 5/28/12 6/1/12
  Parking Lot Paving-Grounds 5/28/12 6/1/12
  McCloskey Field Replacement 6/4/12 8/3/12
Duquesne Towers
  Design Build Flash Tank
  Upgrade Floors 15th and 16th 5/7/12 8/13/12
  Add Laundry Riser 5/7/12 7/27/12
  Toilet Rooms 9th, 10th and 11th Floors 5/7/12 7/27/12
  Hogan Dining Center/Addition 4/16/12 7/27/12
  Replace 1st Floor Cold Water Line
  Furniture Replacement 5/4/12 7/2/12
Saint Ann Hall
  2nd Floor Restrooms Upgrade 5/7/12 7/27/12
  Carpeting and Door Upgrades
Saint Martin Hall
  Furniture Replacement 5/4/12 6/11/12
  Carpeting Replacement 5/7/12 6/4/12
Vickroy Hall
  Cooling Tower Repairs 4/5/12 4/25/12

General Buildings

Administration Building
  1st Floor Restrooms ADA Upgrade 5/7/12 7/30/12
  2nd Floor Restroom Floor Replacement 5/7/12 6/13/12
  5th Floor Restroom ADA Upgrade 5/7/12 7/2/12
  1st Floor Hallway Carpet Replacement 5/28/12 6/11/12
  Grnd Floor Hallway Carpet Replacement 5/7/12 5/21/12
A.J. Palumbo Center
  Arena Lighting Upgrade 5/7/12 6/4/12
  Lower/Upper Roof Replacement 5/7/12 8/13/12
College Hall
  New Carpet Floors 3rd - 6th 5/7/12 7/9/12
Energy Center
  Recondition, 5KV 50-DHP Circuit Breakers 5/21/12 5/25/12
  Chilled Water, Steam and Electric 5/14/12 7/30/12
  Cooling Tower Replacement 5/28/12 6/25/12
Duquesne Union
  Replace 3rd East & West Entrance Doors 5/14/12 6/11/12
 Africa Room Carpet Replacement 5/21/12 5/25/12
  HVAC Replacement 5/7/12 8/6/12
Fisher Hall
  602 Counseling Renovation-Relocation  1/7/13 1/31/13
  Rear Window Replacement 5/7/12 8/13/12
Gumberg Library
  Service Desk Renovation 6/18/12 8/13/12
  Waterproof West Wall 5/7/12 6/11/12
Koren Building
  Replace Fire Alarm System 5/28/12 8/20/12
Laval House
  Split-System Air Conditioning 5/7/12 7/30/12
Libermann Hall
  Life-Safety Upgrades 5/7/12 10/1/12
  609 Lecture Hall Renovation 1/23/12 5/28/12
  General Classroom Upgrades 5/7/12 7/9/12
  Advancement Move to 1st Fl Mezzanine 6/4/12 7/9/12
Mellon Hall
  340, 340A, 212, 214, and 217 Lab Renovation 3/26/12 5/18/12
  408A, 416, 416A, 434, 452 Lab Renovation 5/7/12 8/13/12
  431 and 432 Office Classroom Renovation 5/7/12 8/6/12
  Exterior Painting 5/7/12 7/13/12
  New Batteries Switchgear
Parking Garages
  Forbes-Structural Inspection 4/5/12 4/5/12
  Forbes-Sealing Floors 1-4 Repairs 6/4/12 8/13/12
  Locust-Lighting Upgrade All Floors 5/7/12 8/20/12
  Locust-Structural Inspection, Repairs 4/5/12 4/5/12
  Locust-Painting Railing Locust Side 5/7/12 7/2/12
Rockwell Hall
  Fire Alarm System Upgrade 5/7/12 11/5/12
  Replace Roofs On 4 Overhangs 5/7/12 6/11/12
  Planter, Retaining Wall, Limestone Cleaning 5/7/12 5/28/12
Trinity Hall
  Chilled Water Lines Tunnel to Rangos 4/9/12 5/28/12
  Fan Coil Unit Replacement 5/7/12 8/13/12
Roadway/Sidewalk Repairs
  Music School, South Sidewalk, Upper Seitz Street 5/7/12 5/28/12
  Music School, Locust-Seitz Add 3 Brick Crosswalks 7/16/12 7/31/12
  AJ Palumbo, Northeast Drive Sidewalk Forbes 6/4/12 6/25/12
  Rangos, Sidewalk Handicap Ramp, Locust McAnulty 5/14/12 5/28/12
  Random Sidewalk Replacement 5/7/12 7/30/12
  Admin Bldg Sidewalk at Main Entrance, McAnulty 7/9/12 7/23/12
  Mellon Hall, Under Overhang, Concrete Repairs 7/9/12 7/23/12
  Locust St-Duquesne Union to Magee Street Mill Asphalt 4/23/12 4/30/12